R E V I S E D     10TH    PL A N   D O C U M E N T   

(2002-2007)

 

            The Bihar State Hydroelectric Power Corporation (BHPC) after being in existence for two decades has reached a point from where it can make a two pronged move. The one will lead to setting up of big hydel units, while the other will remain directed at installing a series of small hydel plants in the State’s canal system.

 

            These will be in accordance with the policy indications from the Centre which clearly emphasize  the need for narrowing the gap between thermal and hydel generation and lay down that  power projects should not be planned only a couple of years before they are expected to become operational. This policy also says  that for their successful commissioning during the 11th Plan, suitable actions should be initiated on specific projects during the 10th Plan period itself.

 

            The BHPC has taken care to prepare a schedule by which its small hydel power stations will become operational within 24 months from the day their execution starts.

 

            In respect to big hydel projects attempts are to be made during the 10th Plan period itself so that they certainly start generating power during the 11th Plan period.

 

            Projects lined up by the BHPC at the end of the first year of the 10th Plan period are as follows:

 

                                    i)         Big hydel projects              -                       690 MW.

                                    ii)        Small hydel projects          -                       150 MW.

 

 

          The BHPC registered under the Companies Act as an Undertaking of the Government of Bihar in 1982 follows a philosophy 3D culture  of DEDICATION, DEVOTION and DISCIPLINE. It is due to this philosophy that the Company is aspiring hard to achieve its objectives of identifying potential of hydro projects, planning & executing them.

 

            The BHPC, in view of the fact that at that point in time it had within its jurisdiction  those hilly areas also which now from part of the new State of Jharkhands paid equal attention  to high, medium and ultra low hydel projects. Efforts have been made to suit parameters and requirements of all three categories of projects.

 

 

 

 

 

 

 

            By the time the new State of Jharkhand came into being (15th November, 2002) the BHPC  had commissioned three projects with an installed capacity of 25MW at places which now fall in Bihar. As many as eight projects with an installed capacity of 35 MW located in Jharkhand are still in the final stages of completion.

 

            Though the creation of Jharkhand as a separate State reduced the area of its operation, the BHPC took it as  a challenge to set up small hydel plants on the plains of Bihar. These SHPs are to be located on the State’s canal systems. At the time of creation of Jharkhand the BHPC had with it 46 DPRs ready for setting up a series of SHPs on the canal system.

 

 

            The BHPC also started looking for locations where big hydel projects could be installed. Its efforts have in this direction met with success to identification of four sites  in the District of Kaimur with a potential of 240 MW of Power. For identifying such locations the BHPC had commissioned the services of the National Hydroelectric Power Corporation.

 

 

            The BHPC, thus, continues to pursue the objective of developing the entire hydel potential and ensuring proper hydro-thermal-mix in power generation in Bihar.

 

 

            The fund received so far by the BHPC since its inception in 1982  for capital expenditure has been as under:-

 

 (i) Authorised Capital                                          -           Rs. 100.00 Crores.

(ii) Subscribed Capital                                          -           Rs.   99.04 Crores

            (iii) As a loan from State Government               -           Rs.   92.94 Crores.

            (iv) Loan from P.F.C                                              -           Rs.     7.07 Crores.

 

            Besides above, the revenue against the sale of energy to the BSEB from BHPC’s commissioned projects has also been availed as and when received.               

 

MANAGEMENT:

 

            Affairs of the BHPC are managed by a Board of Directors headed by  Chairman with the Managing Director acting as its Chief Executive. A team of managers of different functional areas assists the MD and the projects are headed by Project Managers.

 

            The BHPC Board acts in accordance with the general policy guidelines issued by the State Government through its Department of Energy.

 

The BHPC vide a resolution adopted by its Board of Directors in 1997 decided to entrust operation and maintenance of hydel plants to private parties on contract basis.   Dehri, Barun and Valmikinagar plants are being managed accordingly.

 

            As the projects are entrusted to contractors for execution on Trun-key basis, only skeleton staff including Electrical/Mechanical Engineers and Civil Engineers assisted by other staff have been posted to oversee and monitor their progress. 

 

            The Registered office of the BHPC is located at Sone Bhawan, Beer Chand Patel Marg, Patna-800 001

 

FUND

 

The BHPC is a government company as all its shares are fully subscribed by the Government of Bihar or its nominee. Besides contribution towards share capital, the State Government has also sanctioned loans from time to time. Funds received from the Government are utilized by the BHPC according to its own budget duly approved by the Board of Directors. It has also obtained loan from the Power Finance Corporation for meeting the construction expenditure of projects. In addition to these, the BHPC receives subsidies from the Union Government under the latter’s scheme for promotion of non-conventional energy source and also under UNDP Scheme.

 

            The authorised Capital of the BHPC is Rs.100 crores against which Rs.99.04 crores has already been subscribed by the Government.

 

            Three projects viz, Sone Western, Sone Eastern, Eastern Gandak have already been completed and commissioned. For the construction of Eastern Gandak Project, a loan assistance of 1630 million yen had been provided by OECF of Japan under loan agreement.

 

            After the formation of Jharkhand the BHPC had to perforce concentrate on small hydel power stations on all viable sites in Bihar.

 

           POWER SCENARIO IN  BIHAR

 

            With the formation  of the Jharkhand State  which was carved out of it, there resulted substantial reduction in the installed capacity, both  thermal  and hydel in Bihar.  The Sikidri Hydel Power  Station with an installed capacity of 130 MW, meant mainly for operation during peak period except in rainy season when it is to run for all the 24 hours, fell in Jharkhand. The Patratu Thermal Power Station with 840 MW  installed capacity also went to the new State.  The Tenughat Thermal Power Station  is also likely to be transferred to Jharkhand. The Bihar State is thus left with the following generating  stations only:-

 

 

 

SL.

NO

Name of the Project.

Installed Capacity

(MW)

                (i)        Barauni Thermal Power Station(derated)                        210

               (ii)        Muzaffarpur Thermal Power Station                               220

              (iii)       Kosi Hydel Power Station                                                  20

              (iv)        Valmikinagar Hydroelectric Power Station                      15

               (v)        Dehri Small Hydel Power Station                                    6.6

               (vi)      Barun Small Hydel Power Station                                     3.30

                                                                                                 Total =         474.90

 

            Against the above installed capacity, the generation at the above  power stations is lower. Even in hydel power stations mentioned above, due to shortage of water, which  depends on the irrigation demand in the canal system, the full generating  capacity is seldom achieved. Considering  the  installed capacity of hydel and thermal, the hydro-thermal-mix is 10:90  against ideal required mix of 40:60.

 

The 16th Power Survey assessed  the power and energy demand of Bihar  (untruncated outside D.V.C area) as follows:-

Year

                                                            1999-00              2000-2001              2001-2002

Energy Demand in M. Kwh           10765                         11492               12222

Peak Load (MW)                               2048                         2186                 2325

                                                                                                                                               

 

 

            Even the above demand forecast was based on the suppressed demand in Bihar at the time of the 16th Power Survey, because of the fact that there is inadequate transmission, distribution network to meet the total demand of the State outside D.V.C. Valley.

 

            The above energy demand and peak load demand projected in the 16th Power Survey was for Bihar as a whole. So far separate Power Survey for Bihar has not been done, but considering the 50:50 ratio of power demand in Bihar and Jharkhand, the immediate scenario emerges as follows:-

                                      Year

1999-00

2000-01

2001-02

5288

1024

5746

1093

6111

1163

 

Energy Demand in M.Kwh

Peak Load (MW)

 

            It could thus be seen that against the installed capacity available in Bihar, the energy and peak load demand of Bihar is much more than its installed capacity. Some power is also availed from NTPC sources. Even there is acute shortage of power in the State. It, therefore, calls for harnessing the hydro-power potential wherever available in the State.

 

 

HYDROELECTRIC POTENTIAL OF BIHAR STATE.

 

1.         BIG HYDEL:

 

            A.         Indrapuri ( 450 MW)

 

 

            After creation of Jharkhand state the per capita power consumption index of Bihar came down to 60 against the national average of 344. The Government of  Bihar asked for an economic package from the Centre for its energy sector which had included a demand for the total value of Rs. 930 crores for the development of both small and big hydel power projects. This also covered Indrapuri HE Project (6 x 75 MW) known earlier as the Kadhwan Reservoir project. The proposal was examined in detail by the Planning Commission which recommended vide its Power & Energy Division U.O. No. 1-26/1-/2/2000-P&E  of 20.10.2000 for a provision of Rs. 500 crores for a period of 10 years for small hydroelectric project to generate 72 MW of power. But as regards Indrapuri  Reservoir Project (old Kadhwan), the Planning Commission observed that since        it is a multipurpose project a view on this project would take substantial time.

 

            But execution of this project, is necessary not only to create much needed additional peaking hydroelectric power generating capacity but also to provide stability to the existing Sone Canal System which has sustained the economy of  at least seven districts of Bihar since 1886. This canal system has been facing threat of water shortage due to construction, after independence, of a number of dams in the Sone  basin before the river enters Bihar. A schematic diagram showing  such dams is  enclosed as Annexure – I.

 

            Even as Government of Bihar and the BHPC were looking at the     possibilities of executing this project with distinct components of irrigation and hydel power generation, the NHPC approached the Government of Bihar with      a request that they be allowed to take it up for execution. The Government of  Bihar agreed to this hoping that the project would be taken up in the Central sector and necessary clearances would be obtained by the executing agency, NHPC  themselves. To ensure that its execution did not face any problems with the State Government at any stage it named the BHPC to be the nodal agency for this project.

 

            But the Ministry of Power, Government of India is yet to notify this project    under section 18A of the Electricity Supply Act,1948 for execution under Central sector through the NHPC.

 

            The cost of the project has been estimated at Rs.1111.14 crores (at 1996 price level), which includes Rs. 533.36 crores for irrigation and Rs. 577.78 crores for power generation.

 

            A meeting was convened by the Member (Hydro), Central Electricity Authority on 25.11.2002 in New Delhi to find out ways for early notification of  this project under section 18A of the Electricity Supply Act,1948 for its execution in the Central sector. A copy of the minutes of the meeting held on 25.11.2002 is enclosed as Annexure – II.

 

            From the minutes of the meeting it would appear that a number of steps    are required to be taken before the Union Ministry of Power could consider notification of this project under section 18A of the Electricity Supply Act 1948 for getting this project executed in the Central Sector.

 

            In view of this the Government of Bihar has approached Ministry of Power for financial tie up of this project with international funding agencies so that this Project can be implemented at the earliest. Delay in implementation of this Project  is adversely affecting the irrigation and power sectors of this State.

 

            If this Project is taken up in the Central Sector and a notification under  section 18A of Electricity Act of 1948 is issued by the Ministry of Power, a sum of   Rs.10 crore will have to be made available for this Project immediately.   

            B.        Pumped Storage Schemes :

 

            As stated above, hydel potential of 240 MW has been identified    on the basis of reconnaissance survey for installing pumped storage plants in    Kaimur district as detailed below:-

 

 

Sl. No.

Site of proposed Pump Storage Scheme

Parent River

Height of Fall

(M)

Location

Proposed installed capacity in MW

1.

2.

3.

4.

5.

7.

1.

Telhar Kund

Fall

Sura

(Left)

80

Block-Adhaura

Vill- Gudri

 

60 

2.

Sinafdar

Fall

Sura (Right)

130

Block – Adhaura

Vill – Salea-Dahar

 

60 

3.

Panchgotia

Fall

Karsotha

102

Block –Adhaura

Vill-Chorpania

 

60 

4.

Hathiadah and Durgawati falls

Hathiadah & Durgawati

145

Block – Adhaura,

Vill – Londo

 

60 

 

240 MW

 

                       

            The reconnaissance survey included Civil design, Geology, Hydrology, environment along with collection of requisite data such as gauge and  discharge, meteorological observations, contour plans etc.

 

 

            The BHPC is actively examining the possibility of a joint venture with  NHPC to accelerate progress on above mentioned schemes. The NHPC is known    for its resource mobilisation capacity in terms of manpower, knowledge, material, equipment etc.

 

 

            Frequency excursion in the Eastern Region is a well-known phenomenon.  Very often for more than 50% of the time during a month, the frequency remains  beyond the band 49 hz – 50.5 hz. On average for about more than 1½ hr. a  day, the frequency remains below 48.5 hz. and for about 6 hrs a day the frequency moves up beyond 51 hz. (EREB Report for June, 2002). The damage  to power stations due to this range of frequency variation is very serious but  unfortunately this is not discussed often. Damage to equipment, due to  abnormal frequency variation, at the consumer’s end is another major area of concern. NHPC in a recent paper has estimated that loss to the nation due to low  and high frequency related energy loss is to the tune of about Rs.3400 cr. If we add to this the cost of equipment damage at the power plants and at the    consumer’s  end,  the  amount  will  be  very  high,  indeed.  The  pumped  storage   scheme will utilise the off-peak power to generate power during peak period. As a result, thermal plants will be able to function as base load stations improving the   PLF of the region thus bringing down the per unit cost of generation as also  helping to lower the high frequency during lean hours and maintain correct frequency during peak-load period. Supply of peak power will cater to the peak  demand and will make the low frequency rise to acceptable level during peak    demand hours. This frequency stabilisation, will not only benefit West Bengal but         also the entire region. This project thus is a project for the grid and, therefore,        should have been the responsibility of the Central Government and not of any        state alone.

 

            The BHPC has also requested the NTPC to adopt identified pump storage schemes of Bihar for execution. This will help the BHPC fall in line with    the Centre’s  policy enunciated by the Union Power Secretary, Sri R. V. Sahi in his  key-note address to Dr. K. L. Rao Centenary celebrations. The Union Power  Secretary in his address had observed that pumped storage schemes should be       identified and   executed on priority basis in view of the present mismatch between demand and supply. A copy of the letter addressed to NTPC has also been forwarded to the Ministry of Power, Government of India, and CEA. A copy of the said letter along with enclosure is enclosed as Annexure – III.

 

                        However, the following activities are yet to be completed before taking up   the preparation of a DPR:-

 

(a)               Establishment of G&D stations and rain gauge stations and taking  observations for the duration required for the necessary study.

 

(b)               Essential geological/geophysical surveys for establishment of type of dam/barrage and its foundation and other civil structures.

 

(c)               Required topographic survey in the project area.

 

(d)               Establishment of essential temporary infrastructure and access roads required for carrying out the work.

 

(e)               Preliminary environmental survey.

 

(f)                 Analysis of hydrological data.

 

(g)               Power potential studies.

 

(h)               Preparation of cost estimate.

 

            Keeping this in view the BHPC propose to have DPRs prepared by the NHPC at an estimated cost of Rs. 2 (two) crores.

 

2.         Small Hydel Projects:

 

            (A)       Commissioned Projects:

 

                        There is potential of 140 MW for setting up small hydroelectric power projects in Bihar.

 

            Out of this, the following three hydroelectric power projects of 25 MW installed capacity have already been commissioned by availing the consultancy   of CEA/CWC:-

 

 

Sl. No.

Name of Hydel Project

Installed Capacity

(in MW)

Year of Commissioning

 

1.

Sone Western,

Dehri-on-Sone

 

4x1.65  =  6.6

1993

2.

Eastern Gandak, Valmikinagar

 

3 x 5    =  15.0

1995

3.

Sone Eastern, Barun

 

2 x 1.65 = 3.3

1996

 

                        Externally Aided Schemes:

 

                        Eastern Gandak Canal HE Project (3 x 5 MW), is the only   externally aided project in Bihar.

                        Project No. & Title    :           ID-P.31, Eastern Gandak Canal HE  Project.

 

(ii)               PERFORMANCE OF COMMISSIONED PROJECTS:

 

                        Performance of the Corporation in respect to commissioned projects is summarized below:-

 

                        FOR LAST 6 (SIX) YEAR

 

 

Sl. No.

Year

Target (MU)

Achievement (MU)

% Achievement

1.

2001-02

55.5

51.7

93

2.

2000-01

55.5

49.3

89

3.

1999-2000

55.5

44.5

80

4.

1998-99

55.5

44.6

80

5.

1997-98

55.5

48.4

87

6.

1996-97

55.5

47.7

86

 

            The Energy Department, Government of Bihar, after creation of Jharkhand, approached the Union Government for an economic package totaling Rs. 16,825 crores. This included a demand for RS. 360 crores for execution of 46 small hydel projects on the State’s canal systems for creation of an additional power generation capacity of 72 MW.

 

 

            As all major thermal and hydel stations fell within the territory of the new state,  the Government of Bihar decided that the BHPC should  take up execution of 22 small hydel projects out of 46 in the first phase so that at least 25 MW of additional electricity  was available within 24 months. The Government of Bihar prioritised these projects in the following order:-

 

 

Sl. No.  First Phase

Sl. No. Second Phase

Sl. No. Third Phase

1.              Agnoor 

¼2x500 KW

1.          Sipaha 

¼2x500 KW

1.          Amethi

¼1x500 KW

2.             Triveni 

¼2x1500 KW

2.         Belsar

¼2x500 KW

2.          Natwar 

¼1x400 KW

3.           Dhelabag

            (2x750 KW)

3.         Paharma

          (2x500 KW)

3.     Rampur

       (1x250 KW)

4.           Nasariganj

    (2x500 KW)

4.          Sebari

 (2x500 KW)

 

5.             Tejpura

  (2x750 KW)

5.             Rajapur                                            

(1x700 KW)

 

6.          Jainagara

 (2x500 KW)

6.       Walidad

(1x750 KW)

 

7.             Dhoba

RD – 43.00 (of T.M.C.)

 (2x1000 KW)

7.          Dehara

(2x500 KW)

 

8.           Katanya

RD – 79.00 (of T.M.C.)

(2x1000 KW)

8.         Arwal

(1x500 KW)

 

 

9.             Barwal

 RD – 124.00(of T.M.C.)

 (2x800 KW)

9.       Shirkhinda

(2x350 KW)

 

10.         Mathouli

RD – 311.50(of T.M.C.)

(2x400 KW)

 

 

 

            The Union Ministry of Power when approached for providing financial assistance for these projects requested the Union Ministry of Non-conventional Energy Sources (MNES) vide its OM No.37/03/2001-III of 10.01.2001 for needful action in the matter.

 

            But the MNES has been experiencing difficulties in providing financial assistance to Bihar because of provisions contained in Annexure – “C” of its administrative order circulated vide its letter no. 14/2/2000/SHP of 19.05.2000 which are as follows:-

 

Scheme

Areas

Upto 1 MW

Above 1 MW & upto 5 MW

Above 5 MW & upto 15 MW

Capital subsidy for State sector projects

NE Region Sikkim

Equipment cost+50% of Civil cost upto Rs.60,000/- per KW

Equipment cost+25% of civil cost upto Rs. 4.5 crores per MW

Equipment cost + 25% of civil cost limited to

Rs.22.50 crores/  project.

 

Middle Himalayas, Ladakh, A&N

Equipment cost+50% of Civil cost upto Rs.45,000/- per KW

Equipment cost+25% of civil cost upto Rs. 3.00 crores per MW

Equipment cost + 25% of civil cost limited to

Rs.15.00 crores/ project.

 

Other areas (only notified hilly regions)

Equipment cost+50% of Civil cost upto Rs.30,000/- per KW

Equipment cost+25% of civil cost upto Rs. 1.50 crores per MW

Equipment cost + 25% of civil cost limited to

Rs.7.5 crores/ project.

 

 

            Subsidies, therefore, could not be released for execution of Bihar’s hydel projects on canal sites even if the State, because of its geographical compulsions, has little choice and few options in the matter. It may also  be noted in this connection that while some of the North Eastern states like Arunachal Pradesh and Manipur entitled for MNES subsidies, have per capita power consumption varying from 80 to 128 units, the Bihar’s per capita power consumption is only 60 units. In North Bihar, where most of canal site hydel projects would be located, the per capita power consumption is just about 20 units.

 

            Because of uncertainties in respect to the Economic Package and technical difficulties in obtaining subsidies from the MNES the  BHPC took up execution of six out of 10 projects identified for the first phase with its own revenue surplus and with the hope that grants would be made available for these in due course. These projects are – Agnoor, Triveni, Dhelabagh, Nasriganj, Tejpura and Jainagara.

 

Renovation and Modenisation of Running Units:

 

            Hydel power units at Barun (2x1.65MW) in Aurangabad, Dehri (4x1.65 MW) in Rohtas and Valmikinagar (3x5 MW) in  West Champaran were commissioned at a time when the Bihar State Hydroelectric Power Corporation (BHPC) was facing a serious resource constraint, to the extent that a sum of Rs. seven crores had to be taken as loan from the Power Finance Corporation at a prohibitive interest rate of 16.75% per annum.

 

            The BHPC, till date, have paid an amount of Rs. 14.0 (Fourteen) crores in servicing of this loan and still carries a liability of Rs. 7.0 (Seven) crores on this account.

 

            With the commencement of generation at Barun, Dehri and Valmikinagar the BHPC managed to tide over the financial crisis substantially as they started yielding revenue. It is also worth mentioning here that the first Bulb Turbine unit manufactured by the BHEL in India is installed in the Hydel Power Station at Dehri-on-Sone and Barun. These stations have speciality of having no outside / projected power house building.

 

            But it also needs to be mentioned that although Barun, Dehri and Valmikinagar were commissioned, the BHPC at that point in time was financially not in a position to have everything that a modern hydro station would need. Work on the canal could not be undertaken as per the DPR. The emphasis was to  achieve operation of these stations with the limited resources available at the time. In fact, the BHPC has operated these stations with minimum essential operating systems. These units have the potential to become more viable with incorporation of certain features that would help augmentation in their output.

 

             The AHEC, IIT Roorkee had been assigned by the BHPC with the task to prepare the detailed project reports for renovation and modernisation of these 3 SHP stations. In September,2001, they submitted their report. The estimated cost in respect of Renovation and Modernization of these three projects is given in two parts as below :-

 

(i)                  Estimate for those machines/equipment/installations which need extensive maintenance / replacement."

 

(ii)                "Estimate for those items(system) which could not be provided at the time of commissioning (System Improvement for increasing generation).

 

 

A.        Barun Project (2 x 1.65 MW)      

                                                                                                  Cost in Rs. Lacs

S. No.

Items

Machines/

Equipment/

Installations

which need extensive maintenance/

replacement

 

System Improvement for increasing generation

Total cost

1.

Civil Works

113

562

675

2.

E & M Works

39

-

-

39

3.

T & D

95

-

-

95

4.

Miscellaneous

-

-

46

46

 

Total

247

608

855

 

B.   Dehri on Sone SHP Project (4 x 1.65 MW)

1.

Civil Works

173

1106

1279

2.

E & M Works

54

-

54

3.

T & D

70

-

70

4.

Miscellaneous

-

47

47

 

Total

297

1153

1450

 

C.     Valmikinagar Project (3x 5 MW)

1.

Civil Works

302

2979

3281

2.

E & M Works

196

-

196

3.

T & D

-

-

-

4.

Miscellaneous

-

50

50

 

Total

498

3029

3527

 

Grand Total

1042

4790

5832

 

 

 

            Bihar could also not benefit from the MNES schemes of renovation, modernization and uprating of capacity because the scheme notified vide Annexure –‘D’ of the Ministry’s letter no. 14/2/200-SHP of 19.5.2000 was applicable only to those projects that had been completed by the end of the 8th Plan i.e. by 31.3.1992. The hydel projects of the BHPC for a total capacity of 25 MW were completed after this date.

 

 

CAPITAL MAINTENANCE

 

 

            Two units of Dehri and one each of Barun and Valmikinagar have already  run beyond prescribed limit specified by the manufacturer.

 

            The BHPC proposes to undertake Capital Maintenance of four nos. of units  during 2003-2004. A sum of Rs. 200 lacs i.e.@ Rs. 50 lacs per unit will be required.

 

 The total cost involved in R&M works along with capital maintenance is estimated at Rs. 22.00 crores.

 

 On-going Hydel Projects :-

 

            Small hydel projects in Bihar are being executed with technical collaboration and back up of AHEC, IIT, Roorkee. Their status is summarised as under:- 

 

On Going Projects :-   

    

                                                                                                (Amount in lakh)

Sl. No.

 

 

Name of the Scheme

 

 

Location

 

 

 

Installed Capacity (K.W.)

 

Cost of the Project

 

Outlay for 2002-03

 

 

Exp. upto 30.11.2002

 

 

(1)

(2)

(3)

(4)

(5)

(6)

(7)

1

Agnoor

Arwal

2 x 500

797

500

300

2

Triveni

W.Champaran

2 x 1500

1347

Nil

250

3

Dhelabagh

Rohtas

2 x 750

670

Nil

35

4

Nasariganj

Rohtas

2 x 500

568

Nil

25

5

Jainagra

Rohtas

2 x 500

531

Nil

25

6

Tejpura

Aurangabad

2 x 750

664

Nil

30

 

New Hydel Projects:

 

                        It was also decided to take up work, immediately, for projects whose DPRs were ready as per the phase decided by the Government of Bihar.

 

                        Steps are underway to add 12 MW capacity to the State’s power system by setting up of 10 hydel projects by 31.03.2005. Details of these projects are as under:-

 

 

 

 

 

Name of the Scheme

Location

Features

 

 

 

 

 

Status

 

 

 

District

 

Installed Capacity No. of Units size (KW)

Annual Energy (M.U.)

Cost of the Project

(Rs.in lacs)

1

2

 

5

6

7

 

 

NIT issued.

Last date of submission of offer

1.  Dhoba

W.Champaran

2 x 1000

11.57

977

 

2.  Katanya

-do-

2 x 1000

11.39

987

 

3.  Barwal

-do-

2 x 800

8.71

800

 

4.  Mathauli

-do-

2 x 400

4.19

546

 

5.    Dehra

Aurangabad

2 x 500

6.95

584

NIT issued.

Last date of submission of offer -  05.02.2003.

 

 

6.   Sipaha

Aurangabad

2 x 500

6.86

543

 

7.   Belsar

   ehanabad

2 x 500

6.03

570

 

8.   Shirkhinda

Rohtas

2 x 350

5.35

487

 

9.   Paharma

-do-

2 x 500

8.00

555

 

10.. Sebari

-do-

2 x 500

7.50

568

                                                                                       Total   Rs. 6617 Lacs

   

 

 Tenders for the above 10 sites are being evaluated by AHEC, Roorkee.

 

 

ADVANCE PLANNING

 

 

            For exploration of new projects, it is necessary to get detailed survey and investigation done for all probable sites. It is also necessary to get the detailed project report prepared for such projects which, after survey and investigation, appear viable. For survey and investigation and for preparation of detailed project report, therefore, sufficient funds have been provided in the 10th Plan outlay.

 

 

            The survey and investigation of six probable sites on the Gandak Canal System in Gopalganj District is in progress. It may be necessary to conduct survey and investigation of districts of Jamui, Munger and Bhagalpur which have potential for small hydel power projects on the canal system as well as for run-of the river projects. Provision for this has also been made in the 10th Plan outlay.

 

            Besides, the BHPC propose to renovate and modernize the Kataiya hydel plant (4x5 MW) which is being transferred to it from the BSEB. The BHPC will move the MNES for financial support for the R & M scheme of the plant which has been running at the derated capacity of one MW for many years.

 

 

 

ACHIEVEMENTS OF 9TH PLAN:

 

By the end of the 8th Plan, the BHPC had commissioned 3 Hydroelectric Power Projects with a total installed capacity of 25 MW and was striving to get other projects executed through private entrepreneurs as per the policies of Government of India. But the BHPC could not succeed in this endeavour. Private  entrepreneurs  did  not come forward to set up power stations in Bihar. Such a situation appeared to continue because neither private entrepreneurs were coming forward nor setting up of hydel power stations for various reasons. But this stalemate may not prevail for long as it has been decided by the Government to set up hydel power stations through the Bihar State Hydroelectric Power Corporation without waiting for the participation of private entrepreneurs.

 

            The   Bihar State Hydroelectric   Power   Corporation   (BHPC)   is   installing 22 (twenty two)  small  hydel  power  stations  at  canal  fall  sites  in  Sasaram,  Aurangabad, Buxar, West Champaran and Supaul districts of Bihar under the Government of India’s scheme of rural electrification.     

 

During the 9th Plan period the BHPC got the DPR for Sankh Hydroelectric Project for an installed capacity of 186 MW prepared by CEA/CWC. The project has now gone to Jharkhand.

 

Achievement in 2002-03

 

 

             During first year of the 10th Plan period i.e., 2002-03 the BHPC took forward the activities/projects that were initiated around the end of 9th Five Year plan. Among these mention may be made of the following:-

 

 

(i)          Identification on the basis of reconnaissance survey completed by NHPC   four sites for   big hydel plants in Kaimur district with a total capacity  of 240MW.

 

(ii)         Commencement of execution of 5 (five) SHPs (Total capacity 8 MW) on canal systems of the State utilising surplus revenue of the Corporation.

 

 

(iii)     With the completion of Agnoor SHP the BHPC will be adding one MW capacity to the State’s power system.

 

(iv)        Revival of the proposal to set up hydel units (450 MW) as a part of Indrapuri Project (formerly known as Kadhwan Multi-purpose   project)  with active support of the Central   Electricity Authority(CEA) and the Central  Water Commission(CWC).

 

(v)        Arrangement for training of operational staff at  the IIT,Roorkee,Alternate   Hydro   Energy  Centre (AHEC),Roorkee-247 667 (Uttaranchal), and  National Water Academy, Pune- 411024.

 

Projects in Jharkhand :-

 

       In addition to its assignments in Bihar the BHPC continues to be responsible for completion of projects in Jharkhand for a total capacity of 35 MW. The status of these projects indicating requirement of funds is as on 1.11.03 given below:                                                      

                                                                                                                          ( Rs. in lakh)

Sl. No.

Name of SHPs.

Installed Capacity (MW)

Estimated cost

Expenditure incurred

Fund required to complete the Project

 

Budget for

2003-04

1.

Chandil

8.0

3249.0

3067.0

982.0

700

2.

North Koel, Mandal

24.0

4734.0

3600.0

1134.0

300

3.

Tenu Bokaro

1.0

386.0

220.0

166.0

100

4.

Sadani

1.0

549.0

219.0

381.0

300

5.

Lower Ghaghri

0.4

329.0

125.0

275.0

200

6.

Netarhat

0.05

50.0

5.0

45.0

50

7.

Nindighagh

0.2

150.0

10.0

140.0

100

8.

Jalimghagh

0.2

200.0

30.0

170.0

150

Total:-

1900

 

           

            The BHPC has been drawing the attention of the Government of Jharkhand towards the fact that it could not more ask the Government of Bihar to make financial allocations for projects located in Jharkhand. It would, therefore, be necessary that the Government of Jharkhand may make available to be BHPC funds required for completion of these projects. This has also been brought to the notice of the Union Ministry of Non-conventional Energy Sources (MNES) and the Union Ministry of Power. The BHPC hopes that funds would be made available soon and the completion of ongoing projects would add an additional capacity of 35 MW to Jharkhand’s Power System during the 10th Plan itself.

 

Conclusion : -

           

            The Government of Bihar, after creation of Jharkhand, asked for an economic package for the State from the Centre. The Energy sector’s requirement included in the package was to the tune of Rs.16,825 crores. The requirement of the hydel power development alone was estimated at Rs.930 crores.

 

            The Planning Commission after examining the proposal made the following recommendations vide their U.O. no. 1-26/1-/2000-P&E dated 20.12.2002:-

 

                        “Although the State has proposed a requirement of Rs.930 crores for Bihar  State Hydroelectric Power Corporation for taking up Small Hydro Projects for Rs.360.00 crores and Kadhwan Hydro Projects (450 MW) of Rs.570.00  crores. The Kadhwan Hydro Project appears to be a multipurpose project  and the state has submitted the project report to Ministry of Irrigation. A view on the project would take substantial time. For the other small  projects the reports are also to be prepared. In view of this a provision of  Rs.500 crores for a period of 10 years may be recommended”.

 

            A copy of the above referred letter of the Planning Commission, Government of India is enclosed as Annexure -IV  

 

            However, the sources from which this amount was to be made available were not identified. The BHPC, as also the State Government from different levels have taken up this matter with the Union Government so that some of these are implemented in the Central sector.

 

            The Union Ministry of Non-conventional Energy Sources (MNES) has been approached to amend its administrative order no.14/2/2000/SHP of 19.05.2000 to pave way for release of subsidies for Bihar’s new hydel projects and renovation and modernisation of its running power houses.

 

            For big hydel units like the Indrapuri Reservoir Project (earlier known as Kadhwan Multi-purpose project) or at places identified in Kaimur ranges, the Union Government has been requested either to arrange a tie-up with international funding agencies or execute them as a Central scheme through Central Power Sector Undertaking like the National Thermal Power Corporation (NTPC) or the National Hydroelectric Power Corporation (NHPC).        

 

 

            The requirement of fund and capacity addition is expected as follows:-

 

 

 

2002-03

2003-04

2004-05

2005-06

2006-07

Eleventh Plan

 

Fund

(Rs. in lakhs)

 

2150

7843

6592

3942

4090

74078

Capacity Addition (MW)

 

1.0

5.0

20.00

2.8

5.0

737

 

           

            Project-wise expenditure is detailed in the enclosed list as Annexure-A.

 

 

            The amount of Rs. 78.43 crores will be utilised for creation of an additional capacity of 5 MW during the year 2003-04 in Bihar. In addition, preliminary work on hydel unit (450 MW) of the Indrapuri (Formerly named as Kadhwan Multi-purpose Project) and 4 (four) pumped storage schemes in the Kaimur district with a total capacity of                 240 MW will be started. The Indrapuri Hydel Power unit and the pumped storage scheme of the Kaimur district are expected to become operative by the middle of 11th Five Year Plan.

 

Annexure - IV

PLANNING COMMISSION

(Power & Energy Division)

 

 

 

 

          Subject: Comments of Power & Energy Division on Bihar Package

 

 

Pr. Adviser (SP-Bihar) may kindly refer to his letter dated 18th October, 2002 regarding meeting on Bihar Package. As decided in the meeting, Power & Energy Division has examined the Bihar Package in regard to Power Sector. Our observations are given in the enclosed note.

 

This has the approval of Pr. Adviser (Energy).

 

 

L.P. Sonkar

Joint Adviser (Power)

Pr. Adviser (SP-Bihar)

 

 

 

 

            Planning Commission U.O.No. 1-26/1-/2/2000-P&E dated 20th., October, 2000.

 

 

 

 

 

 

PLANNING COMMISSION

(Power & Energy Division)

 

Sub:    The observation of Power & Energy Division on the Proposal of  newly  created  Bihar State for             Development of  Power Programmes.

 

 

State Plan Division has requested for the comments of Power Division on the proposal of fund requirements for Power sector for the new State of Bihar. The total requirement of funds for Power sector is Rs. 16825 crores as per the following break  up :

 

Rs. Crores

Generation                                                                  665

Transmission                                                               739

Rural Electrification                                                      255

Distribution                                                                  250

Navi Nagar Thermal Project                                       8000

Bihar State Hydro Power Corporation                          930

Total                                                                           16825

 


The erstwhile Bihar has now been bifurcated into Jharkhand State and Bihar State. The development of power sector in the erstwhile State of Bihar was the responsibility of (i) Bihar State Electricity Bihar (BSEB), (ii) Tenughat Vidyut Nigam Ltd. and (iii) Bihar Hydro Power Corporation.

 

The total installed capacity in erstwhile Bihar as on March 2000 was 1988 MW (comprising 174.90 hydel and 1813.50 thermal). Bihar State was also having share in the Central power projects located in the Eastern region to the extent of 37.85% which works out to 968 MW. In addition to above Bihar was getting 60% of total electricity generated by Damodar Valley Corporation (DVC) having total installed capacity of 2552 MW. Therefore, the total installed capacity of erstwhile Bihar including share in the central projects and in the DVC projects was 4487MW. Inspite of this  capacity,   State  was  having  a  peaking  shortage  of 16% and  energy shortage of 6.3%. Out of this shortage, it is understood that the shortages in the new State of Bihar would be about 80 MW peaking (35% of total peaking shortage in the erstwhile Bihar) and 197 million units energy shortage (35% of total shortage in erstwhile Bihar State).

 

The Transmission Distribution (T&D) losses although state has indicated 22% in 1999- 2000, in   reality it   is much  higher   and the  losses are more in the newly formed Bihar State because of mostly domestic, commercial and agricultural load compared to Jharkhand State. PLF was as low as 20% compared to 67.31 all India level. After the bifurcation, the new State of Bihar will have only 598 MW of installed capacity out of total 1988 MW of installed capacity of erstwhile Bihar which are as under :-

MW

 


 Kosi                                                                              20

 Barauni Thermal                                                         320

 Muzaffarpur                                                                220

 Sone Western Link                                                       10

 Eastern Gandak                                                           15

 P.E.S.U.                                                                        13

598

 

It may be seen from the above that new State of Bihar will have only 30% of the capacity of the total installed capacity of the erstwhile Bihar and the demand of Bihar will be about 35-40% of the demand of erstwhile Bihar. This is mainly because most of the industrial load are in Jharkhand State whereas load in the Bihar is only in domestic, commercial and agriculture sector.

 

Apart from 598 MW installed capacity in the State, State will have also share in the Central projects. As it is a fact that Eastern region has surplus power which is being proposed to evacuate to Northern and Southern region, it would be advisable that State should initially concentrate on development of transmission and distribution systems not only to meet their existing demand but also to develop the load in domestic, commercial and irrigation sector. It is also to be noted that PLF of Baruni Thermal Power Station located in Bihar is much below the 15% PLF. Therefore, there is need to take up renovation and modernisation of this plant on priority basis. Further, it is to be noted that Planning Commission had sanctioned Mujaffarpur TPS extension (2x250 MW) in Bihar State in December) 1995 but due to constraints of re-sources no action so far has been initiated for implementing this project. Therefore, on generation side the priority goes to setting of up this project.

 

The proposal also contains two projects namely Barh STPP project, stage I, 2000 MW and Navi Nagar project to be implemented by NTPC. As far as Navi Nagar project is concerned, no action so far has been initiated by NTPC whereas Barh project in district Patna has been identified as a mega project and site specific study has been initiated by NTPC and Feasibility Report is under finalisation.

 

Keeping the above factors in view, States should take up the power programmes as envisaged in the proposal as per the following priorities.

 


Name of the Scheme                                                              Rs. crores.

 

1.         Renovation and modernisation (R&M)

(i) Existing thermal power station at Baruni                                          300

(320 MW)

(ii) Muzaffarpur Thermal Power Station

(existing capacity 2x110 MW)                                                              120

(iii) Kosi Hydel Power Station19 MW                                                        1

Rs. 421 Cr.

 

 

JUSTIFICATION

 

Barauni Power Station is presently working at less than 15% PLF. Unit No.6 and 7 are not working. With the investment of Rs. 300 crores in R&M, the units would be in a position to operate at optimal load and PLF may improve to 40%. With Rs. 300 crores the cost per MW of renovation works out less than Rs. one crore whereas for the new project of this size the cost could be around Rs. 12000 crores. Therefore this needs to be supported.

 

II. Transmission & Distribution (T&D)

 

i) Transmission 739

 

ii) Distribution 250

 

These works need to be completed in there to five years period so that the State could avail power to be purchased from surplus State like Jharkhand and the Central sector. The completion of the above work would also expected to reduce T&D losses in the State.

 

 III. Rural Electrification (RE)

 

In the erstwhile Bihar about 71% of the villages have been electrified per 1990-91 census. The left out villages are about 19635. It is not clear how many villages are to be electrified in the newly state of Bihar. However, State has proposed a requirement of As. 255 crores for this purpose. It we go by a norm of As. 7 lakhs per village, it works out to 3643 villages. We can agree to this amount of Rs. 255 crores for a period of 10 years.

 

 

IV. Hydro Development

 

Although the State has proposed a requirement of As. 930 crores for Bihar State Hydro Power Corporation for taking up small hydro projects for As. 360 crores and Kadwan Hydro project (450 MW) at As. 570 crores. The Kadwan hydro project appears to be a multi-purpose project and the State has submitted the project report to Ministry of Irrigation.

 

A view on this project would take substantial time. For the other small projects the reports are also to be prepared. In view of this a provision of As. 500 crores for a period of 10 years may be recommended.

 

V. Generation

 

Muzaffarpur Thermal Power Station (2x250 MW) was earlier sanctioned by Planning com- mission in Dec. 1995 at As. 1452 crores. The State could not take any initiative due to constraint of resources. Now the Sate has proposed a requirement of As. 22.50 crores out of which initial payment of BHEI could be around As. 200 crores. This need to be supported. This project could be completed in 5 years period.

           

As per the above priority an amount of Rs. 4420 crores against the proposal of Rs. 16825  crores may be recommended for a period of 10 years as per the following break up:

 

      Rs. crores

 

 i) R & M                                                 421

ii) T&D                                                   994

iii) Rural Electrification                           255

iv) Hydro Development                          500

v) Generation                                      2250

4420

 

 

As far as NTPC projects to be taken up to Navi Nagar and Barh (Mega Projects) the funding will be from the Ministry of Power's budget. Therefore the requirement of funds for these l, two projects have not been included in out recommendation above.

 

The recommended amount of Rs. 4420 crores is basically to be funded from State Plan as against Rs. 1032 crores in the 8th Plan and first three years of the 9th Plan. So far the erstwhile  Bihar State was giving a priority less than 6 to 7% to the Power sector which was one of the lowest power sector allocation by the State in the country. The newly created State of Bihar need to  allocated minimum 20% of the share of all sectors' outlay for power programme. For  this purpose they have to mobilise the resources. This could be only possible if the State set up a Regulatory Commission for fixing up the tariff primarily and reform and restructure the utility system in order to make it more efficient and accountable and conducive to private sector investment.

 

Annexure – III

 

No. 3677/                                                                                 Patna, the  2.12.02  /

 

From:

            L.P. Sinha,

            Managing Director

 

To,

            Shri Valmiki Prasad,

            Executive Director (Eastern Region),

            National Thermal Power Corporation Ltd.,

            2nd Floor, Lok Nayak Bhawan,

            Dak Bunglow Road,

            Patna – 800 001

 

Sub:-   Regarding execution of identified Pumped Storage Schemes in Bihar.

 

Ref:-    Keynote address of Shri R.V. Shahi, Union Power Secretary at Dr. K.L. Rao  Centenary celebrations on July             14, 2002 at Hyderabad.

 

Sir,

 

            I have come across the keynote address of Shri R.V. Shahi, Union Power Secretary to the Dr. K.L. Rao, Centenary celebrations on the 14th July, 2002 which had identified the challenges being faced by the power sector in the country as also had outlined the strategy to deal with these problems.

 

            Shri Shahi, in course of his address had noted that peaking support had  emerged as a major challenge to the smooth operation of all regional grids in the    country and the load profile necessitated substantial load shedding during peak hours and similarly backing down of available capacity during off-peak hours. He had emphasised the importance of augmenting hydro capacity to provide peaking support in view of the mismatch that existed in all regions of the country between demand  and supply leading to precariously low frequency of operations.

 

            The Union Power Secretary had pointed to the economic advantage of  pumped storage plants saying their costs would vary to the extent of fuel cost of    pumping power. Besides, he had said, pumped storage capacity at existing sites  would also reduce the duty of existing plants whose efficiency  was on decline due to ageing.

 

 

            Shri Shahi had, therefore, advised the NTPC to identify in every region, pumped storage scheme and other hydro stations that would be developed by them. This would be both in the interest of the NTPC as also for a balanced system  operation.

 

            I am happy to let you know that BHPC as already got hills  of Kaimur and  Munger districts of Bihar surveyed by the NHPC for identification of possible sites for pumped storage  plants.

 

            The report submitted by the NHPC has identified four such sites with a total capacity of 240 MW in the Kaimur district of Bihar. The details of these sites are as under:-

 

Sl No.

Site of           proposed           Pump Storage Scheme

Parent River

Height   of  Fall

Location

Proposed

installed capacity           in MW

 

 

1.

2.

3.

4.

5.

7.

1.

Telhar Kund

Fall

Sura

(Left)

80M

Block-Adhaura

Vill- Gudri

 

60

2.

Sinafdar

Fall

Sura

(Right)

130 M

Block – Adhaura

Vill – Salea-Dahar

 

60

3.

Panchgotia

Fall

Karsotha

102 M

Block –Adhaura

Vill-Chorpania

 

60

4.

Hathiadah and Durgawati falls

Hathiadah & Durgawati

145 M

Block  - Adhaura

Vill – Londo

 

60

 

240 MW

 

            It is requested that the NTPC may kindly let the BHPC know about the  interest it would have in these projects in view of the observations as above made by the Union Power Secretary so that further necessary action for execution of these projects in power starved state of Bihar may be decided accordingly.

 

                                                                                    Yours faithfully,

                                                                                    Sd/-

                                                                                    (L.P. Sinha)

                                                                                    Managing Director

 

Memo No.  3677/                                                                     Patna, the 2.12.02/

            Copy forwarded to Chairman, National Thermal Power Corporation, Corporate Centre, NTPC Bhawan, Scope Complex – 7, Lodhi Road,  New Delhi – 110 003 for his kind information and necessary action.

 

 

                                                                                    Sd/-

                                                                                    (L.P. Sinha)

                                                                                    Managing Director

                                                                                   

 

Annexure - II

Government of India

Central Electricity Authority

Hydro Project Appraisal Division

Sewa Bhawan, R.K. Puram,

New Delhi – 110 066

 

 

                        No. 502/14/2002-HPA/865                                                                 Dated 26th Nov. 2002.

 

Subject:        Summary Record of   Discussions   of Meeting   taken  by Member (Hydro), CEA on 25.11.2002 to review the progress of   Kadhwan    Hydro Electric Project.

 

 

            Please find enclosed herewith minutes of meeting taken by Member  (Hydro), CEA on 25.11.2002 to review the progress of Kadhwan Hydro Electric Project.

 

                                                                                                                       

Encl: As Above.                                                                                                    Sd/-

                                                                        (Tanmoy Das)

                                                                        Director(HPA)

                                                                                               

 

 

1. Shri Yogendra Prasad, Chairman-cum-Managing Director, National Hydro Electric Power Corporation             Ltd., NHPC Office Complex, Sector-33,Faridabad – 121 003. Fax No. – 915-277941                                                          

2.  Shri L.P. Sinha, Managing Director, Bihar State Hydro Electric Power  Corporation, Sone Bhawan, Birchand Patel Marg, Patna – 800 001.

Fax No 91-612-227692

 

3. Shri Bal Mukund, Executive Director(PLG), National Hydro Electric Power Corporation Ltd., NHPC Office Complex, Sector-33, Faridabad – 121 003. Fax    No. 915-277941

 

4. Chief Engineer, PAO, CWC, Sewa Bhawan, R.K. Puram, New Delhi.

 

5. SA to Member (Hydro), CEA.

 

 

Central  Electricity  Authority

 

 

 

 

Minutes of the Meeting held on 25.11.2002 in CEA, chaired by Member(Hydro) to discuss various  points  involving  Kadhwan Reservoir project (Renamed as Indrapuri Reservoir Project)

 

1.         List  of participants is enclosed.

 

2.         Member (Hydro) welcomed the participants and stated that the  purpose of the meeting is to identify the various critical issues which needs to be sorted out before NHPC can proceed further towards                       implementation of the Project.

 

3.         Various  issues regarding Indrapuri Reservoir Project (Kadhwan Multipurpose project) are discussed in the meeting and a brief  summary is given below:-

 

a) Kadhwan Reservoir project has been renamed as Indrapuri Reservoir project  and envisages construction of a dam, 45m high across river Sone in Rohtas district of Bihar and Garhwa district of Jharkhand. Submergence by this project as per DPR of 1998 as intimated by CWC during the meeting, in the state of Bihar, Jharkhand, UP and MP  are as given below:-

 

 

                                    Bihar & Jharkhand                 8556  ha.

                                    U.P.                                       16199 ha

                                    M.P.                                           345 ha(in river portion)

                                                            Total             25100 ha.

 

            b)         47 villages as given below are affected:

 

                                    M.P.                                        Nil

                                    Bihar & Jharkhand                 17

                                    U.P.                                         30      

 

 

c)         The water released from the dam shall firm up to help existing Sone Canal   irrigation   system   downstream   of Indrapuri barrage and Bihar shall be able to utilize its share of water from Sone River as per Bansagar agreement of 1973. The DPR of the power component was earlier prepared by Bihar State Hydro Electric Corporation(BHPC) and irrigation component by Water Resources Department, Government of Bihar(GOB). A composite  DPR was submitted in 1998 to CWC (however, copy was not sent to CEA) by the Water Resources Department, GOB after comments were received from CWC on the DPR submitted in 1987. The estimated  cost of the project is as given under:

 

                        Irrigation Components                      Rs.   533.36 cr.

                        Power Components                           Rs.   577.78 cr.

                        Total                                                   Rs. 1111.14 cr.(At 1996 price level)

 

d)         The Managing Director of BHPC indicated that Government of Bihar is very keen in taking up this project and complete it in minimum possible time. MOP was requested vide letter  dated 5th September, 2001 that project may be entrusted to NHPC subject to certain conditions.

 

e)         CWC intimated that as there would be submergence in the State of UP, Jharkhand, MP & Bihar, consent of UP, Jharkhand & MP would be required for this project. CWC stated that the Inter-State matters are under examination in CWC.

 

f)         Regarding environmental and forest clearances of the project, although necessary action has been initiated, this has to be further persued. NHPC enquired whether any reserved forest/ wild life sanctuary/national park are involved in the submergence area.

 

g)       i)        Notification under Section 18(A) is yet to be issued by MOP in favour of NHPC for this project. NHPC expressed their willingness to take up this project as a multipurpose project in the Central Sector  Project for which notification under Section 18(A) need to be issued by Ministry of Power in favour of NHPC. The following actions are to be taken immediately  in respect to this project, before notification is issued by Ministry o Power.

 

 

         ii)         CWC shall write to the involved States to give their concurrence for the project to be taken as central sector project for execution through NHPC. NHPC shall provide all assistance in expediting clearance from involved states as it was felt that NHPC is having their local officers in the involved states. CWC should complete this exercise at the earliest. CEA will review the process of the follow up  action again in January 2003 and decide future course of action for early execution of this project.           

 

 

List of  Participants

 

 

                                    Central Electricity Authority

                                    1.         Shri B. K. Aggarwal, Member(Hydro).

                                    2.         Shri M. Subramanian, Chief Engineer (HPA), Incharge.

                                    3.         Shri Tanmoy Das, Director(HPA)

 

                                    Bihar State Hydro Power Corporation Ltd.

                                    1.         Shri L.P. Sinha, Managing Director.

                                    2.         Shri S.R.N. Biswas, Advisor.

                                    3.         Shri K. K. Pathak, Executive Engineer.

                                    4.         Shri J. Lall, Project Manager.

 

                                    National Hydro Electric Power Corporation Ltd.

                                    1.         Shri Bal Mukund, Executive Director.

                                    2.         Shri R.K. Sharma, Director(The.).

 

                                    Central Water Commission

                                    1.         Shri S.K. Srivastava, Director PAO(N)

 

Annexure - I

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


Bihar State Hydroelectric Power Corporation Ltd.

Revised Tenth Plan Outlay

(2002 - 2007)

Sl. No.

Name of Project

Installed Capacity     (in MW)

Estimated cost              (in lakh)

Expenditure upto 30.11.2002

Tenth Plan

Eleventh Plan

2002-                2003

2003-2004

2004-2005

2005-2006

2006-2007

2007-2012

(A) ON GOING PROJECTS

 

 

1

Agnoor

1.00

797.00

300.00

500.00

-

-

-

-

-

2

Triveni Link Canal

3.00

1347.00

250.00

200.00

700.00

197.00

-

-

-

3

Dhelabagh

1.50

670.00

35.10

135.00

450.00

50.00

-

-

-

4

Nasariganj

1.00

568.00

25.00

125.00

350.00

68.00

-

-

-

5

Jainagra

1.00

531.00

25.00

110.00

350.00

46.00

-

-

-

6

Tejpura

1.50

664.00

30.00

130.00

450.00

54.00

-

-

-

(B) RENOVATION & MODERNISATION 

1

Capital Maintenance & Renovation of Gates & Construction of escapes etc. at Dehri,Barun, Valmikinagar

25.00

6032.00

-

200.00

2200.00

1200.00

1400.00

1030.00

-

(C)  NEW PROJECTS (CANAL FALL SHPs) 

 

1

 Dhoba

2.00

977.00

-

50.00

500.00

427.00

-

-

-

2

Kattanya

2.00

987.00

-

100.00

300.00

587.00

-

-

-

3

 Barwal

1.60

800.00

-

50.00

340.00

410.00

-

-

-

4

Mathauli

0.80

546.00

-

80.00

246.00

220.00

-

-

-

5

Dehra

1.00

584.00

-

50.00

350.00

184.00

-

-

-

6

Sipaha

1.00

543.00

-

50.00

280.00

213.00

-

-

-

7

Belsar

1.00

570.00

-

100.00

280.00

190.00

-

-

-

8

Shirkhinda

0.70

487.00

-

50.00

337.00

100.00

-

-

-

9

Pharama

1.00

555.00

-

70.00

200.00

285.00

-

-

-

10

Sebari

1.00

568.00

-

50.00

200.00

318.00

-

-

-

11

Rajapur

0.700

347.00

-

-

-

247.00

100.00

-

-

12

Walidad

0.750

372.00

-

-

-

240.00

132.00

-

-

13

Arwal

0.500

318.00

-

-

-

218.00

100.00

-

-

14

Amethi

0.500

324.00

-

-

-

224.00

100.00

-

-

15

Natwar

0.400

214.00

-

-

-

14.00

100.00

100.00

-

16

Rampur

0.250

222.00

-

-

-

50.00

100.00

70.00

-

(D) ADVANCE PLANNING

 (a)

Canal Fall

12.00

7200.00

-

-

-

200.00

500.00

700.00

5800

(b)

Run of River

19.00

11400.00

-

-

-

200.00

300.00

400.00

10500

i)

Indrapuri

450.00

57778.00

-

-

100

200.00

300.00

500.00

56678

ii)

Pumped Storage Plant

 

 

 

 

 

 

 

 

 

a)

Telhar Kund

60.00

-

-

-

50

110.00

200.00

320.00

-

b)

Sinafdar

60.00

-

-

-

50

110.00

200.00

320.00

-

c)

Panchgotia

60.00

-

-

-

50

110.00

200.00

320.00

 

d)

Hatiadah & Durgawati Fall

60.00

-

-

-

50

110.00

200.00

320.00

-

Survey, Investigation & Preparation of DPR

 

100.00

19.00

10.00

10.00

10.00

100.00

Fund Required (Rs. in lakh)

 

 

2150.00

7852.00

6592.00

3942.00

4090.00

  73,078.00

Capacity  Addition (MW)

 

 

1.00

5.00

20.00

2.80

5.00

737.00

 

 

 

 Introduction | Corporation Profile | Tenth Plan | Tender | Contact us | Feedback